On 16th July, the Supreme Court issued judgement in the case of Triple Point Technology and PPT. The appeal raised three main issues, firstly the provision of liquidated damages when contract had been terminated. The second & third issues related to construction of clauses limiting remedies.
Paul acted as counsel for Triple Point in the Supreme Court arguing the liquidated damages point. Paul has given a summary of the decision in this video.
For more like this, subscribe to the 39 Essex Chambers YouTube channel or click here for more videos.